Pune: PMC Intensifies Citywide Road Repairs During Monsoon Lull; Over 3,300 Potholes Fixed

Pune Pothole Repair
Share this

Pune News, June 23, 2025: Seizing a brief break in monsoon rains, the Pune Municipal Corporation (PMC) has accelerated road repair and maintenance operations across the city. The civic body is employing multiple techniques to address potholes and damaged stretches, particularly in areas affected by waterlogging and early monsoon damage.

WhatsApp Channel

According to PMC’s Road Department, out of 3,377 potholes identified citywide, 3,331 have already been repaired, leaving only 46 remaining. This swift response follows extensive road damage caused by heavy early monsoon showers and clogged stormwater drains.

Despite pre-monsoon preparations, intense June rains washed away much of the groundwork. Media reports and citizen complaints about deteriorating road conditions pushed the administration to act quickly. With hot asphalt now available from PMC’s asphalt plant, repairs have resumed at full speed in both central and suburban areas.

Five-Pronged Repair Strategy

PMC has adopted five different repair methods based on material availability and site conditions:

  • Hot Asphalt – Used where dry conditions allow.
  • Cold Bag Mixes – Applied where hot mix isn’t feasible.
  • Chemical and Concrete Repairs – For durable patchwork.
  • Paver Blocks with Gravel/Concrete Fill – Ideal for deep potholes and poorly drained roads, like the Katraj-Kondhwa stretch.
  • Traditional Patchwork – Used for particularly deep or hazardous potholes.

Additional Maintenance Efforts

Beyond potholes, the Road Department has also:

  • Repaired 388 roadside chambers
  • Resolved 125 water-logging hotspots

Progress Snapshot

CategoryStatus
Total Potholes Identified3,377
Potholes Repaired3,331
Remaining Potholes46
Road Chambers Repaired388
Water-Logging Sites Fixed125
Material Used12,257 tonnes
Asphalt Area Repaired18,235 sq. meters

Aniruddha Pawaskar, Head of PMC’s Road Department, stated, “Despite challenges in procuring hot asphalt during rains, we’ve repaired over 3,000 potholes. We’re also using paver blocks and concrete where needed. Work will continue as long as dry conditions last.”

PMC has urged residents to cooperate with ongoing repairs and assured continued efforts to ensure safer roads throughout the monsoon.